General Contractor: INTERCOR Sp. z o.o.
08/2023-present
The construction of the S6 expressway between the Skórowo junction and the Leśnice junction, a section of the S6 Słupsk - Bożepole Wielkie expressway, began in Pomerania in August 2023.
The construction works will include the construction of a section of the S6 expressway with a length of about 10.88 km (section from km 29+174.13 to km 40+054.45), along with the construction of a road interchange - "Leśnice" and Places of Service for Travelers (Darżewo cat I) and 25 engineering structures (14 animal crossings and 11 overpasses).
The general contractor is the company Przedsiębiorstwo Usług Technicznych " INTERCOR " Sp. z o.o. Our first machines started work on September 6, 2023. We are the only earthwork contractor on this construction site. Our section includes the following works :
removal of the humus layer -350,000m3
excavation of trenches- 1,052,000 m3
replacement of non-bearing soil- 250,000 m3
execution of embankments- 870,000 m3
construction of an overload embankment or working platform- 11,000 m3
improvement of embankment layers with hydraulic binder - 580,000 m2
layer of improved soil C0.4/0.5 - 140,000 m2
macro leveling - 300,000 m3
substructures - 450,000 m2