General Contractor: P.U.H. Rajbud sp. z o.o.
The task in question includes track work on railroad line No. 234 from km 11+030 to km 19+898 (a section with a total length of 8.868 km) and on railroad line No. 229 from km 24+400 to km 31+000 (a section with a total length of 6.600 km). The total length of the track on the task in question is 15.448 km
To perform according to the contract we have:
● excavation in the amount of-50000m3
● spreading of unsorted gravel 20-25cm thick in the amount of about 20000m3