1. Home
  2. Projects
  3. Construction of the S7 expressway on the section Miłomłyn- Olsztynek

Construction of the S7 expressway on the section Miłomłyn- Olsztynek

General Contractor: STRABAG Sp. z o.o.,

STRABAG Infrastruktura Południe Sp. z o.o.

 

This section is part of an investment with a total length of about 20.1 km, which was divided into two implementation tasks: C1 Ostróda Południe - Rychnowo (8.8 km) opened to traffic on August 11, 2017, and C2 Rychnowo - Olsztynek Zachód (11.2 km The investment consisted in the construction of a section of the S7 dual carriageway expressway, together with the construction of service roads, the repair of selected local roads, the construction of engineering structures and environmental protection facilities). The total length of the sections we implemented is 9.2 km of main line, 19.1 km of service roads, 1.7 km of connecting roads. We executed 23 tanks, 2 traffic circles, HIGHWAY SERVICE STATION. We started the work in July 2015 and completed it in November 2016.

 

Within the scope of the contract, we performed, among others:

● dehumusification 582,298 m3

● soil replacement 56,605 m3

● excavation 978,122 m3

● embankments 761,591 m3

 

We worked most of the contract in two-shift mode, which allowed us to complete the task extremely quickly.

They say we are the best
Check it out!

ul. Dworcowa 29,

83-331 Przyjaźń

+48 666 615 640
biuro@firmarichert.pl