Expansion of TNG PERN Gdańsk oil terminal - Stage II

General Contractor: POLIMEX BUDOWNICTWO Sp. z o.o. Sp.K.

 

Our task was to construct the working platforms, the substructure over the heads of the columns and the structures for the oil tanks. All 3 tanks have an internal diameter of 70 m and a nominal capacity of 100,000 m 3 each. The foundation work lasted from March to June 2019. The culmination of our work was the execution of a 10 cm layer of mma as a leveling layer for the bottom of the tank. In total, we made about 18,000 m 3 of the foundation with gravel, 3,500 m 3 of aggregate substructure and 11,500 m 2 of asphalt.